Workshop 2: Workload Planning
Overview
Building on the foundations established in Workshop 1, this session focuses on detailed workload planning and migration strategy development using Dr Migrate’s advanced planning capabilities. The workshop leverages the platform’s integrated assessment tools to transform high-level goals into actionable migration plans through detailed application analysis and strategy development.
Workshop Objectives
- Develop detailed application migration strategies using Dr Migrate’s assessment framework
- Define modernization targets and approaches using the platform’s analysis tools
- Create preliminary wave plans with the Wave Planning feature
- Establish TCO baselines using built-in calculators
Expected Outcomes
- Documented application strategies in Dr Migrate
- Modernization roadmap with defined targets
- Initial wave planning in the platform
- Preliminary TCO analysis results
Pre-Workshop Preparation
- Enable advanced assessment mode Configure assessment templates Verify user access levels Test TCO calculator access
- Updated application inventory from Dr Migrate Technical documentation Assessment templates from platform Business motivation responses
- Application owners and SMEs Enterprise architects Technical leads Business stakeholders Infrastructure team
Workshop Structure
App Strategies (45 minutes)
Strategy Development Process
Using the App Strategy Module:
- Access the Application Strategy section
- Review TIME methodology guidance
- Use the pre-filled strategy matrix template
- Document decisions in the platform
- Generate strategy reports
Key Activities:
- Application categorization using templates
- Pattern identification
- Stakeholder input capture
TIME Methodology Framework
Strategic Horizons:
- TIME: 2-4 year strategic horizon
- 6R: 1-2 year tactical horizon
TIME Categories:
-
Tolerate: Maintain current state
- Applications that are fit for purpose
- No immediate investment needed
- Regular review required
- Limited to Retain or Rehost treatments
-
Invest: Enhance capabilities
- Applications with high business value
- Technical improvements needed
- Strategic investment required
- Multiple treatment options available
-
Migrate: Move to cloud
- Applications ready for cloud
- Business value justifies move
- Technical compatibility exists
- All 6R treatments possible
-
Eliminate: Decommission
- Applications with low value
- Technical debt or risk
- No future investment planned
- Focus on data retention
Treatment Alignment:
- Review potential conflicts between TIME and 6R
- Document rationale for treatment decisions
- Consider business priorities
- Evaluate technical constraints
Modernization Targets (45 minutes)
Platform Services Assessment
End-of-Life Management:
-
Operating Systems
- Identify unsupported versions
- Plan upgrade paths
- Consider cloud alternatives
- Document dependencies
-
Databases
- Review version support
- Evaluate migration options
- Plan data migration
- Consider PaaS alternatives
Modernization Opportunities:
-
Data Services
- SQL Server to Azure SQL
- Oracle to Azure Database
- NoSQL to Cosmos DB
- Data Warehouse to Synapse
-
Web Applications
- IIS to App Service
- Java to Azure Spring Apps
- PHP to App Service
- Node.js to App Service
-
Application Services
- Windows Services to Functions
- Batch Jobs to Logic Apps
- Message Queues to Service Bus
- File Processing to Blob Storage
Cloud Service Selection
Service Categories:
- Platform Services
- Backup (Recovery Services Vaults)
- Domain Services (AD, Entra)
- Storage Solutions
- Secret Management (Key Vault)
- Remote Access (AVD, Bastion)
- Patching and Monitoring
- Security Center
- Email and Collaboration
- Infrastructure as Code
- Code Management
Selection Criteria:
- Technical compatibility
- Business requirements
- Cost implications
- Operational impact
- Security considerations
- Compliance needs
Implementation Strategy:
- Service prioritization
- Migration sequencing
- Integration planning
- Testing approach
- Rollout strategy
Platform Activities:
- Run the Modernization Targets Assistant
- Review automated mapping results
- Modify decisions as needed
- Discuss and document modernization choices
- Map cloud service requirements
- Discuss compliance needs
Migration Planning (45 minutes)
Application Sizing Assessment
Using the Application Sizing Module:
- Access the Application Sizing section
- Review complexity ratings for each application
- Analyze migration effort indicators
- Consider technical dependencies
- Evaluate business impact
Key Metrics:
- Application complexity score
- Migration effort estimation
- Technical dependencies count
- Business criticality rating
- Risk assessment factors
Wave Planning Process
Using Wave Planning Tools:
- Access the Wave Planning module
- Use the AI Assistant to generate a wave plan based on application affinity and complexity wave planning mapping
- Review and modify wave suggestions
- Set wave criteria
- Generate timeline views
Key Features:
- AI-powered dependency analysis
- Automated wave plan generation
- Timeline visualization
TCO Analysis (45 minutes)
TCO Summary Review
Key Focus Areas:
- Overall scope of assessment (applications, servers, storage)
- Current on-premises costs vs. projected cloud hosting costs
- Annual savings breakdown
- Key savings contributors (right-sizing, reserved instances, hybrid benefits)

Example TCO Summary showing cost comparison and savings breakdown
Azure Cost Analysis
Review Components:
- Compute costs breakdown
- PaaS service projections
- Storage requirements and costs
- Backup, DR, and networking expenses
- Total cost comparison with percentage savings
Highlight Assumptions:
- Reserved Instance selections
- Hybrid Benefit applications
- Treatment-specific configurations (Rehost, Replatform, etc.)
- Production vs. Non-Production settings
IaaS Cost Comparison
Walk Through Scenarios:
- As-Sized PAYG baseline costs
- Impact of Azure Hybrid Benefits
- Reserved Instance savings (1-year vs. 3-year)
- Right-sizing cost reductions
- Combined optimization savings

Monthly Azure costs comparing different optimization scenarios
Intel Optimization Benefits
Demonstrate Optimization Impacts:
- Core reduction opportunities
- Database license savings
- Performance improvements by application
- Server-specific optimization recommendations
- Overall cost and performance benefits

Performance and cost benefits from Intel-optimized configurations
Accessing the Report:
- Navigate to the Insights section
- Select Advanced Migration Insights
- Allow 5-10 minutes for report generation
- Use Power BI interactive features to explore details
Essential Points to Cover:
- Annual savings potential
- Key optimization levers
- Performance improvement opportunities
- Next steps for optimization
Migration Decision Workshop (45 minutes)
Application Review Process
Consultant Actions:
- Request customer to identify 2-3 representative applications for detailed review
- Access Advanced Report in Dr Migrate
- Review key data points:
- Application inventory details
- Dependencies and integrations
- Application Complexity
- Application TCO
- Overall TCO
- Business value indicators
Key Discussion Points:
- Validate inventory mapping, adjust as required.
- Review automated recommendations
- Discuss TIME categorization
- Evaluate 6R treatment options
- Consider modernization opportunities
Stakeholder Engagement
Key Stakeholders:
- Application owners and SMEs
- Enterprise architects
- Technical leads
- Business stakeholders
- Infrastructure team
- Security and compliance teams
Engagement Process:
-
Initial Review
- Present treatment recommendations
- Share rationale and evidence
- Gather initial feedback
- Document concerns and questions
-
Validation Workshop
- Deep dive into specific applications
- Review technical constraints
- Discuss business impacts
- Address stakeholder concerns
- Document decisions and rationale
-
Endorsement Process
- Present final recommendations
- Address remaining concerns
- Secure stakeholder sign-off
- Document approvals
Treatment Documentation
Required Documentation:
- Application inventory with treatments
- TIME and 6R mappings
- Treatment rationale
- Technical constraints
- Business impacts
- Risk assessment
- Cost implications
- Timeline considerations
Communication Materials:
- Executive summary
- Detailed treatment matrix
- Cost-benefit analysis
- Risk register
- Implementation timeline
- Resource requirements
Treatment Validation
Validation Criteria:
- Technical feasibility
- Business alignment
- Cost effectiveness
- Risk mitigation
- Timeline viability
- Resource availability
Review Process:
-
Technical Validation
- Architecture review
- Dependency analysis
- Performance assessment
- Security evaluation
- Compliance check
-
Business Validation
- Value assessment
- Impact analysis
- Stakeholder alignment
- Risk acceptance
- Cost approval
-
Implementation Validation
- Resource planning
- Timeline verification
- Dependency mapping
- Risk mitigation
- Success criteria
- Choose diverse application types Include critical systems Consider different complexity levels Select from various business units
- Business value alignment Technical compatibility Resource requirements Risk assessment Timeline constraints
Decision Framework
Review Process:
- Present Advanced Report findings
- Validate TIME assessment results
- Confirm 6R treatment recommendations
- Document stakeholder feedback
- Finalize migration decisions
Key Outcomes:
- Validated migration approach
- Documented rationale
- Stakeholder endorsement
- Next step actions
Summary Document Preparation (30 minutes)
- Application strategy decisions TIME and 6R mappings Modernization targets Migration waves Stakeholder actions
- Microsoft/Partner engagement Detailed planning initiation Resource allocation Timeline development
Workshop Deliverables
- TIME methodology outcomes 6R treatment decisions Modernization opportunities Wave planning draft
- Azure-ready applications Modernization targets Dependency mappings Resource requirements
- Microsoft workload review Partner selection criteria Engagement timeline Resource planning
Consultant Guidance
- Focus on applications with clear Azure migration potential
- Use Advanced Report to validate decisions
- Document all assumptions and constraints
- Ensure stakeholder alignment on decisions
- Prepare for Microsoft/Partner engagement
- Complete inventory validation
- Stakeholder availability
- Technical documentation
- Business motivation alignment
- Resource commitment
- Identified Azure migration candidates
- Validated migration strategies
- Stakeholder endorsement
- Clear next steps for Microsoft/Partner engagement
- Documented decisions and rationale
Post-Workshop Follow-up
Documentation Distribution
- Workshop minutes and decisions Application strategy matrix Modernization roadmap Wave planning draft TCO analysis results
- TIME assessment templates 6R framework guide Technical requirements Risk assessment logs Action item tracker
Stakeholder Communications
Communication Plan
Distribution List:
- Workshop attendees
- Application owners
- Technical leads
- Business stakeholders
- Program sponsors
- Infrastructure team
Key Information to Share:
- Workshop outcomes and decisions
- Individual application strategies
- Next phase timeline
- Action items and owners
- Follow-up meeting schedule
Action Items Tracking
- Distribute workshop summary Share assessment results Schedule follow-ups Confirm decisions
- Complete assessments Validate strategies Begin detailed planning Engage partners
- Finalize migration waves Resource planning Budget alignment Execution readiness
Follow-up Sessions
Recommended Sessions
-
48-Hour Checkpoint (30 minutes)
- Review workshop outputs
- Address immediate questions
- Confirm action items
- Validate next steps
-
Week 1 Review (1 hour)
- Deep dive into strategies
- Technical validation
- Resource planning
- Risk assessment
-
2-Week Planning (2 hours)
- Detailed migration planning
- Partner engagement
- Timeline development
- Budget refinement
Resource Access
- Assessment dashboards Report access Template library Documentation portal
- Technical support contacts Knowledge base access Community forums Training materials
Next Phase Preparation
Preparation Checklist
-
Documentation Review
- Workshop outputs validated
- Strategies documented
- Decisions recorded
- Actions assigned
-
Stakeholder Alignment
- Business sign-off obtained
- Technical approval secured
- Resource commitments confirmed
- Timeline agreed
-
Technical Readiness
- Assessment data complete
- Dependencies mapped
- Risks documented
- Tools configured
-
Partner Engagement
- Selection criteria defined
- Initial contact made
- Requirements shared
- Timeline aligned